- Plug Power's 15-ton-per-day hydrogen plant in St. Gabriel, Louisiana is on schedule for first-quarter operations, enhancing the North American hydrogen network.
- The project boasts a strong safety record with over 412,000 safe working hours and zero recordable injuries, focusing on rigorous safety management standards.
- The critical dry-out process is underway to ensure high-purity hydrogen production by preventing issues like corrosion and freezing, utilizing advanced pressure regulation techniques.
- The Louisiana plant's expansion to 39 TPD will support demand from key partners like Amazon and Walmart, contributing to Plug Power's strategy of delivering integrated hydrogen solutions.
Plug Power Inc. has confirmed the on-time progress of its 15-ton-per-day hydrogen plant in St. Gabriel, Louisiana, operated in a joint venture with Olin Corporation. The facility, driven by Olin's by-product hydrogen, is in its final commissioning phase and set to bolster Plug's North American hydrogen network. With a keen focus on safety, the project has achieved over 412,000 safe working hours and zero recordable injuries, emphasizing stringent safety management standards. The ongoing dry-out process aims to eliminate moisture and impurities, ensuring the production of high-purity hydrogen. Once operational, the plant will add 15 TPD of liquid hydrogen, expanding Plug's total capacity to 39 TPD to meet the increasing demand. The expansion will cater to partners like Amazon and Walmart, aligning with Plug's strategy of offering vertical integrated hydrogen solutions. Building on operational insights from its Georgia facility, the Louisiana plant will operate round the clock, boosting production efficiency and energy independence. This progress signifies a significant advancement in Plug Power's mission to establish a sustainable hydrogen network across North America.