Clean Power Hydrogen plc Successfully Completes Level 2 Site Acceptance Test in Belfast
Key Ideas
  • CPH2 completes Level 2 Site Acceptance Test for MFE110 electrolyser at Northern Ireland Water's site in Belfast.
  • Test verified functionality, control loops, calibration, and more, marking progress towards hydrogen production.
  • Final commissioning underway with Level 3 SAT expected in Q2 2025, showcasing CPH2's advanced technology in action.
Clean Power Hydrogen plc (CPH2), a UK-based green hydrogen technology and manufacturing company, has successfully completed Level 2 of the Site Acceptance Test (SAT) for its Membrane-Free Electrolyser (MFE) at Northern Ireland Water's site in Belfast. The test verified the functionality of the MFE110 electrolyser through end-to-end checks of various systems. The successful test was conducted by Lagan MEICA Limited and overseen by engineering specialists Arup. Final commissioning has commenced, with the final Level 3 SAT expected in Q2 2025, marking a milestone for CPH2 as their scaled MFE technology becomes fully operational at a customer's site. Jon Duffy, CEO of CPH2, expressed satisfaction with the progress and highlighted the significance of achieving hydrogen production using their innovative technology. This development showcases the advancements in green energy and innovation within the UK, demonstrating a positive outlook for the hydrogen market.
ADVANCEH2

Our vision is to be the world's leading online platform for advancing the use of hydrogen as a critical piece needed to deliver net-zero initiatives and the promise of a clean H2 energy future.

© 2025 AdvanceH2, LLC. All rights reserved.