Adani Energy Solutions Secures Green Hydrogen Transmission Project in Gujarat
Key Ideas
- Adani Energy Solutions has secured a ₹2,800 crore power transmission project in Mundra, Gujarat to enable the production of green hydrogen and green ammonia.
- The project involves upgrading the Navinal electrical substation, adding 765/400kV transformers, and constructing a 75 km long double-circuit line to connect substations.
- The infrastructure boost will enhance AESL's network by adding 150 cKM of transmission lines and 3,000 MVA of transformation capacity, increasing its total order book to ₹57,561 crore.
- The project was secured through a tariff-based competitive bidding mechanism, with the special purpose vehicle transferred to AESL on March 20, 2025.
Adani Energy Solutions has announced the successful acquisition of a significant power transmission project in Mundra, Gujarat, valued at around ₹2,800 crore. This project is essential for providing green electrons to support the production of green hydrogen and green ammonia in the region. The initiative, named the 'Transmission System for Green Hydrogen/Ammonia Manufacturing Potential in Mundra, Gujarat,' will entail the enhancement of the Navinal electrical substation with the incorporation of two substantial 765/400kV transformers. Additionally, a 75 km 765kV double-circuit line will be developed to link the Navinal substation to the Bhuj substation. By bolstering the infrastructure, the project will introduce 150 cKM of transmission lines and 3,000 MVA of transformation capacity to Adani Energy Solutions' existing network, elevating it to 25,928 cKM and 87,186 MVA, respectively. This recent achievement marks the sixth order obtained by AESL during this fiscal year, expanding its total order book to roughly ₹57,561 crore. The competitive bidding process that led to the project's procurement was facilitated by PFC Consulting Limited under a tariff-based mechanism. The project's special purpose vehicle was officially transferred to Adani Energy Solutions on March 20, 2025, signifying a significant milestone in the company's strategic advancements.
Topics
Projects
Renewable Energy
Infrastructure
Energy
Electricity
Project Development
Power Transmission
Order Book
Substation